Summary

IPTC is building three new bus rapid transit (BRT) lines as part of the Marion County Transit Plan (Transit Plan). The vehicles for the BRT system are 60’ articulated BYD all-electric propulsion buses. The lines will have center and curb-side stations. The current mirror on the vehicles protrude from the vehicle and IPTC is concerned that these mirrors may strike passengers at stations or pedestrians at crosswalks.

IPTC ’s goal with this technology is to mitigate safety risks and reduce liability. This technology should also improve the driving experience for IPTC operators.

Procurement Schedule

Request for Information is Released
November 19, 2019 9:00am
Written Questions Due
December 4, 2019 10:00am
IPTC Response Due
December 20, 2019 5:00pm
Vendor Submission of Information Electronically
January 10, 2020 10:00am

Addendums

Download Solicitation

Requested contact information helps IndyGo meet FTA Guidelines in developing bidder’s lists and increases our ability to contact vendors regarding the postings of addenda or other important changes to the solicitation package.  Interested parties can also email us at procurement@indygo.net to request procurement documents.