You can expect construction impacts from 2022 through 2024. Due to the size of the project, the work will take place in phases spread out across six construction areas along the Purple Line corridor to minimize the impact to any one area.
IndyGo will work with the selected contractors to determine final sequence and timing of construction activities. Right now, we are projecting work on 38th Street will start near the State Fairgrounds in spring 2022 and move east. Work on the portion of 38th Street from Shadeland Avenue to Post Road will also be scheduled early in the project. Post Road and the section of 38th Street between Emerson Avenue and Shadeland Avenue are currently scheduled to be under construction towards the end of the project.
Construction Forecast
Purple Line construction is separated into six construction areas as shown on the segment-by-segment map below. Work is projected to start on 38th Street in Spring of 2022 and move east. This section is designed to give a three -week look-ahead of construction activity happening along the corridor and will be updated weekly once construction begins.

Happening Now:
- Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Work will be performed within the lanes that are currently barreled off and is not expected to impact traffic.
- Increased roadway activity continues through September. Two-way traffic is maintained.
Happening Next:
- Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue.
- There will be increased roadway activity throughout September. Traffic is shifted to the inside lanes throughout the segment.
Happening Now:
- The intersection at 38th Street and Orchard Avenue is closed due to an accident unrelated to construction.
- Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Two-way traffic is open using the northern and southern portion of 38th Street.
- Roadway activity is ongoing with intermittent lane shifts throughout the segment. Two-way traffic is maintained.
Happening Next:
- Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Two-way traffic is open using the northern and southern portion of 38th Street.
- There will be increased roadway activity throughout September. Traffic is shifted to the inside lanes throughout the segment.
Happening Now:
- On or after Sept. 29, construction of the Keystone station begins east of the intersection. Work will be confined within the barreled off lanes and not expected to impact traffic.
- Construction of the Meadows station is underway east of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
- Minor activity at the Emerson station continues. Work is confined within the lanes that are barreled off.
- Minor activity at the Arthington station continues west of the intersection. Work is confined within the barreled off lanes.
- Construction of the Emerson Station is in progress on the west side of the intersection. Work is confined within the lanes that are barreled off.
- Two-way traffic is maintained with eastbound traffic shifted to the south half of the roadway and westbound traffic shifted to the north half of the roadway.
Happening Next:
- Two-way traffic is open on 38th Street from Keystone to Emerson avenues following the final configuration. Eastbound traffic is shifted to the south half of the roadway and westbound traffic is shifted to the north half of the roadway.
- Construction of the Keystone station continues east of the intersection. Work will be confined within the barreled off lanes and not expected to impact traffic.
- Construction of the Meadows station continues east of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
- Construction of the Sherman station continues west of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
- Minor activity continues at the Arthington station. Work will be confined within the barreled off lanes and not expected to impact traffic.
Happening Now:
- Access to 38th street will be intermittently closed at various side streets. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.
Happening Next:
- On or after Oct. 3, westbound traffic will be open from Emerson to Shadeland avenues, allowing for two-way traffic in this segment.
- The westbound lane closure between Emerson and Shadeland avenues continues. Motorists driving west can detour around the closure using Shadeland Avenue, 46th Street and Emerson Avenue.
- Access to 38th street will be intermittently closed at various side streets. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.
Happening Now:
- There is intermittent lane shifts and side street closures throughout the segment.
Happening Next:
- There will be intermittent lane shifts and side street closures throughout the segment.
Happening Now:
- On or after Sept. 25, the outside east and westbound lane at the intersection of 56th Street and Post Road will be closed for roadway improvements. Left and right turns will still be maintained using the inside lanes. The closure is expected to last up to 14 days.
- A northbound closure on Post Road from Pendleton Pike to CSX Railroad Crossing has reopened allowing for two way traffic.
- The Lawrence terminus station has mobilized for above ground work.
- The outside north and southbound lanes on Post Rd from CSX Railroad Crossing to Otis Avenue are closed for storm sewer and roadway improvements. Traffic is shifted to the inside lanes.
Happening Next:
- The Lawrence terminus station has mobilized for above ground work.