You can expect construction impacts from 2022 through 2024. Due to the size of the project, the work will take place in phases spread out across six construction areas along the Purple Line corridor to minimize the impact to any one area.

IndyGo will work with the selected contractors to determine final sequence and timing of construction activities. Right now, we are projecting work on 38th Street will start near the State Fairgrounds in spring 2022 and move east. Work on the portion of 38th Street from Shadeland Avenue to Post Road will also be scheduled early in the project. Post Road and the section of 38th Street between Emerson Avenue and Shadeland Avenue are currently scheduled to be under construction towards the end of the project.

Construction Forecast

Purple Line construction is separated into six construction areas as shown on the segment-by-segment map below. Work is projected to start on 38th Street in Spring of 2022 and move east. This section is designed to give a three -week look-ahead of construction activity happening along the corridor and will be updated weekly once construction begins.

1 2 3 4 5 6

Happening Now:

  • Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Work will be performed within the lanes that are currently barreled off and is not expected to impact traffic.
  • Increased roadway activity continues through September. Two-way traffic is maintained.

Happening Next:

  • Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue.
  • There will be increased roadway activity throughout September. Traffic is shifted to the inside lanes throughout the segment.

Happening Now:

  • The intersection at 38th Street and Orchard Avenue is closed due to an accident unrelated to construction.
  • Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Two-way traffic is open using the northern and southern portion of 38th Street.
  • Roadway activity is ongoing with intermittent lane shifts throughout the segment. Two-way traffic is maintained.

Happening Next:

  • Miscellaneous cleanup and minor roadway and pedestrian improvements activity continue. Two-way traffic is open using the northern and southern portion of 38th Street.
  • There will be increased roadway activity throughout September. Traffic is shifted to the inside lanes throughout the segment.

Happening Now:

  • On or after Sept. 29, construction of the Keystone station begins east of the intersection. Work will be confined within the barreled off lanes and not expected to impact traffic.
  • Construction of the Meadows station is underway east of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
  • Minor activity at the Emerson station continues. Work is confined within the lanes that are barreled off.
  • Minor activity at the Arthington station continues west of the intersection. Work is confined within the barreled off lanes.
  • Construction of the Emerson Station is in progress on the west side of the intersection. Work is confined within the lanes that are barreled off.
  • Two-way traffic is maintained with eastbound traffic shifted to the south half of the roadway and westbound traffic shifted to the north half of the roadway.

Happening Next:

  • Two-way traffic is open on 38th Street from Keystone to Emerson avenues following the final configuration. Eastbound traffic is shifted to the south half of the roadway and westbound traffic is shifted to the north half of the roadway.
  • Construction of the Keystone station continues east of the intersection. Work will be confined within the barreled off lanes and not expected to impact traffic.
  • Construction of the Meadows station continues east of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
  • Construction of the Sherman station continues west of the intersection. Work is confined within the lanes that are barreled off and not expected to impact traffic.
  • Minor activity continues at the Arthington station. Work will be confined within the barreled off lanes and not expected to impact traffic.

Happening Now:

  • Access to 38th street will be intermittently closed at various side streets. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.

Happening Next:

  • On or after Oct. 3, westbound traffic will be open from Emerson to Shadeland avenues, allowing for two-way traffic in this segment.
  • The westbound lane closure between Emerson and Shadeland avenues continues. Motorists driving west can detour around the closure using Shadeland Avenue, 46th Street and Emerson Avenue.
  • Access to 38th street will be intermittently closed at various side streets. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.

Happening Now:

  • There is intermittent lane shifts and side street closures throughout the segment.

Happening Next:

  • There will be intermittent lane shifts and side street closures throughout the segment.

Happening Now:

  • On or after Sept. 25, the outside east and westbound lane at the intersection of 56th Street and Post Road will be closed for roadway improvements. Left and right turns will still be maintained using the inside lanes. The closure is expected to last up to 14 days.
  • A northbound closure on Post Road from Pendleton Pike to CSX Railroad Crossing has reopened allowing for two way traffic.
  • The Lawrence terminus station has mobilized for above ground work.
  • The outside north and southbound lanes on Post Rd from CSX Railroad Crossing to Otis Avenue are closed for storm sewer and roadway improvements. Traffic is shifted to the inside lanes.

Happening Next:

  • The Lawrence terminus station has mobilized for above ground work.

Construction FAQs

Read the FAQS below for more details about construction.

IndyGo and DPW have worked together to minimize roadway closures and detours as much as possible. However, for the safety of everyone – construction workers, motorists and pedestrians – some closures will be required. The following is a tentative list of these impacts. The limits and timelines of each closure will be communicated one to three weeks in advance via our regular weekly email communications:

  • 38th Street from Fall Creek Parkway to Orchard Avenue: Closed to both directions of traffic for 10 days.
  • 38th Street from Fall Creek Parkway to Keystone Avenue: Closed to eastbound traffic for 130 days.
  • Keystone Avenue from 34th Street to 46th Street: Closed to both directions of traffic for 10 days.
  • 38th Street from Keystone Avenue to Emerson Avenue: Closed to westbound traffic for 130 days.
  • Sherman Drive immediately north and south of 38th Street: Closed to all traffic for 14 days. East/west traffic on 39th Street will not be impacted.
  • 38th Street and Emerson Avenue intersection: Closed full intersection to traffic for 18 days.
  • 38th Street from Emerson Avenue to Shadeland Avenue: Closed to westbound traffic for 130 days.
  • Post Road from Pendleton Pike to 56th Street: Closed to northbound traffic for 60 days.
  • Otis Avenue from Post Road to Lawrence Village Parkway: Closed to both directions of traffic for 30 days.
  • Wheeler Road from Otis Avenue to Rising Road: Closed to both directions of traffic for 30 days.
  • Wheeler Road from Hawkins Road to 59th Street: closed to both directions of traffic for 30 days.
  • Rising Road from Wheeler Road to Lee Road: closed to both directions of traffic for 10 days.

Detour routes will be available and clearly marked during all roadway or intersection closures. This list is not exhaustive of all traffic impacts and does not include lane or turn movement restrictions (where the roadway remains open). This list is also subject to change to meet construction conditions, upon approval from Indianapolis DPW and through coordination with emergency services. Local access to residences and businesses will be maintained throughout the duration of the project. The best way to monitor impacts during construction will be to register to receive our weekly email communications.

There will be impacts to bus stops and routes when necessary for the safety of riders and/or construction workers. Temporary stops will be provided wherever possible. During times when construction must occur immediately adjacent to bus stops, those stops may need to be relocated or closed temporarily. IndyGo will provide communication about stop closures or relocations, or bus route detours via email communications, on-route announcements and social media.

There may be an increase in traffic on detour routes and side streets. Typical traffic rules and speed limits will apply.

The Contractor will coordinate with the city to provide uninterrupted trash collection.

The Contractor will coordinate with the local post office to ensure continuous mail delivery.

IndyGo will communicate construction updates in a variety of ways including through weekly email messages, social media and website updates. Additionally, our neighborhood liaison, Jarvis Jointer, will be available during business hours to answer questions, share information and attend community meetings at your request. Jarvis’ information is provided on the Purple Line website.

IndyGo is committed to being a good community partner throughout the construction process. IndyGo will provide informational resources, signage and advertising opportunities as part of a Business Toolkit. Additionally, IndyGo has a dedicated construction liaison, Jarvis Jointer, who is available to answer questions and provide additional support. Jarvis’ contact information is available on the IndyGo Purple Line website.

jarvis

Jarvis Jointer

Purple Line Construction Liaison

Jarvis Jointer is an Indianapolis native who earned his civil engineering degree from Purdue University in 2004. He has spent his career in various roles and experiences in civil engineering which include construction administration, site engineering, transportation engineering and environmental engineering. Jarvis has held principal roles and led companies to substantial growth in the local and national marketplace.

As Purple Line Corridor Liaison, Jarvis will serve as a link between construction crews and the community. He will be a resource to businesses and communities throughout the construction process. For questions or concerns about the project, email email jarvis.jointer@indygo.net or call or call 317-661-1964.

Our Current Projects