You can expect construction impacts from 2022 through 2024. Due to the size of the project, the work will take place in phases spread out across six construction areas along the Purple Line corridor to minimize the impact to any one area.
IndyGo will work with the selected contractors to determine final sequence and timing of construction activities. Right now, we are projecting work on 38th Street will start near the State Fairgrounds in spring 2022 and move east. Work on the portion of 38th Street from Shadeland Avenue to Post Road will also be scheduled early in the project. Post Road and the section of 38th Street between Emerson Avenue and Shadeland Avenue are currently scheduled to be under construction towards the end of the project.
Construction Forecast
Purple Line construction is separated into six construction areas as shown on the segment-by-segment map below. Work is projected to start on 38th Street in Spring of 2022 and move east. This section is designed to give a three -week look-ahead of construction activity happening along the corridor and will be updated weekly once construction begins.

Happening Now:
- Miscellaneous cleanup and minor roadway activity continue.
- Two-way traffic is maintained outside of the barreled off dedicated bus lanes.
- Intermittent canopy construction at stations continues.
Happening Next:
- Existing work continues.
Happening Now:
- Miscellaneous cleanup and minor roadway activity continue.
- Two-way traffic is maintained outside of the barreled off dedicated bus lanes.
- Canopy construction of the Orchard and Keystone stations continue.
Happening Next:
- Existing work continues.
Happening Now:
- Two-way traffic is maintained outside of the barreled off dedicated bus lanes.
- Canopy construction of the Arthington, Sherman and Meadows stations continue.
Happening Next:
- Existing work continues.
Happening Now:
- Two-way traffic is maintained outside of the barreled off dedicated bus lanes with intermittent side street closures. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.
- Intermittent canopy construction continues.
Happening Next:
- Existing work continues.
Happening Now:
- Two-way traffic is maintained outside of the barreled off dedicated bus lanes with intermittent side street closures. Adjacent streets will not be closed simultaneously. Local access to all residences and businesses will be maintained.
- Canopy construction at the Richardt and Franklin stations continue.
Happening Next:
- Existing work continues.
Happening Now:
- Two-way traffic is maintained in Lawrence as miscellaneous construction activity continues.
- Station foundation construction of the 56th Street Station is underway south of the intersection. Work is confined within the barreled off lanes and not expected to impact traffic.
- Canopy construction at the Ivy Tech Terminus station continues.
Happening Next:
- On or after Aug. 5, traffic will utilize a four-way stop at the 38th Street and Post Road intersection during the the new light installation.